What counts toward a budget
This is the single most important rule, and it differs by budget kind.A money budget counts approved cost
Utilisation on a money budget is:cost rate × hours for every entry a reviewer has approved, plus any adjustments.
Time that is tracked but not yet approved does not count. It sits in a separate figure, shown under the budget bar as “3.5h awaiting approval”. A tooltip explains it: submitted time is excluded from spent and margin until a manager approves it.
This is why a busy project can show 0% utilisation. Everyone has tracked, nobody has approved. Approve the timesheets and the bar moves.
An hours budget counts everything logged
Utilisation on an hours budget is:What does not count
The forecast
Utilisation tells you where you are. The forecast tells you where you are heading.Completion percentage
Effective hourly rate
Health
Health is a colour derived from the numbers. It is never a field you set.- Red – Over budget
- Amber – At risk
- Green – On track
Any one of these turns a project red:
- the forecast cost exceeds the budget
- utilisation is 100% or more – the budget is consumed
- utilisation leads completion by 25 percentage points or more – you are spending far ahead of progress
Why the 25-point rule matters
A project at 60% utilisation sounds fine. A project at 60% utilisation and 30% completion is not – it is burning budget at twice the rate it is delivering work. On current trend it needs 120% of the budget to finish. The 25-point rule catches that while there is still time to act, rather than waiting for utilisation to cross 100%.When the numbers update
The figures update as facts move, not on a schedule.
The Overview reads a precomputed figure, so it stays fast on a project with a hundred thousand time entries.
Example
Bluebird Coffee – Website Redesign, a $40,000 money budget with a 400-hour total estimate. Work done so far
What the panel shows
Health check
- Forecast cost 40,000 – not over.
- Utilisation 31.25% – under 75%.
- Utilisation minus completion = 31.25 − 62.5 = −31.25 – far from the +25 threshold. The project is delivering faster than it is spending.
- Forecast 36,000) – not approaching.
The Financials panel
On a project’s Overview:
With no budget and no approved time, the panel shows No budget set and a Set budget button instead.
The cost tiles are omitted, not blanked, for someone without
time.viewCost or rate.viewCost. The grid reflows. There is no greyed-out placeholder hinting at a number you are not allowed to see.Permissions
Common questions
Why is my utilisation 0% when the team has been tracking all week?
Why is my utilisation 0% when the team has been tracking all week?
You have a money budget, and none of that time is approved yet. A money budget counts approved cost only. Look for the “awaiting approval” caption under the bar.
Why does an hours budget move immediately?
Why does an hours budget move immediately?
Because an hours budget measures capacity, and capacity is used up the moment someone works. Approval status is irrelevant to it.
My project has no estimates. Is the forecast wrong?
My project has no estimates. Is the forecast wrong?
It is not wrong, it is just not forward-looking. With no estimate there are no remaining hours to project, so the forecast equals the actuals. Add task estimates to get a real forecast.
Can I mark a red project as green?
Can I mark a red project as green?
No. Health is derived, never hand-set. Change the underlying facts – raise the budget, reduce the remaining estimate, clear the overdue tasks, or approve the pending time.
Why is my project amber with only 20% utilisation?
Why is my project amber with only 20% utilisation?
Check the other amber triggers: one overdue task, or five or more entries pending approval, will do it on their own.
Does the completion tick use the same source as the bar fill?
Does the completion tick use the same source as the bar fill?
They are different measures on the same axis. The fill is utilisation (spend). The tick is completion (progress). Seeing the fill run ahead of the tick is the warning sign.
Troubleshooting
Related guides
Set a project budget
Every field on the Budget form.
Hours vs money budgets
Which unit measures what.
Budget alerts
What fires at 50, 75, 90 and 100 percent.
Profitability and margin
Revenue minus cost.
Task estimates
The input the forecast depends on.
Budget vs estimate
Two numbers that are straightforward to mix up.